Project Background

A rapidly growing metropolitan city in Southeast Asia faced critical challenges with its aging sewer infrastructure. The municipal water authority required installation of a new 1.2km sewer pipeline through a densely populated urban area, passing beneath major roadways, existing utility networks, and commercial buildings. Traditional open-cut excavation was deemed impractical due to severe traffic disruption, environmental concerns, and the presence of sensitive underground utilities.

Key Challenges:

  • Installation depth ranging from 6m to 12m below ground surface
  • Navigation through complex geological conditions including soft clay, sandy soil, and mixed ground
  • Strict alignment tolerances (±30mm) required for gravity sewer flow
  • Proximity to existing underground utilities (gas, water, telecommunications)
  • Minimal surface disruption in high-traffic commercial district
  • Environmental regulations limiting noise and vibration levels

Solution: Advanced Slurry Pipe Jacking Machine System

APIE Foundation Equipment (China) Limited provided a comprehensive trenchless solution featuring our HYPERTEC  Pipe Jacking Machine, specifically designed for urban infrastructure projects requiring precision and minimal surface impact.

Technical Implementation

Phase 1: Site Preparation & Launch Shaft Construction

  • Construction of 8m diameter launch shaft using diaphragm wall technique
  • Installation of thrust frame and hydraulic jacking system
  • Setup of slurry separation and recycling plant

Phase 2: Pipe Jacking Operations

  • Installation of 1500mm internal diameter concrete jacking pipes
  • Average advance rate: 8-12m per day
  • Real-time laser guidance system maintained alignment within ±25mm
  • Continuous slurry circulation system for spoil removal and face support

Phase 3: Reception & Connection

  • Precise breakthrough at reception shaft
  • Pipeline connection to existing sewer network
  • Shaft reinstatement and surface restoration

Project Results

✅ Successful Completion: 100% alignment accuracy achieved, exceeding project specifications
✅ Minimal Disruption: Surface traffic maintained throughout 8-month project duration
✅ Environmental Compliance: Zero environmental incidents, noise levels maintained below 65dB
✅ Cost Efficiency: 30% cost reduction compared to traditional open-cut methods
✅ Time Savings: Project completed 2 weeks ahead of schedule

Client Testimonial:

*“APIE’s pipe jacking solution transformed what seemed like an impossible project into a remarkable success. The technical expertise, equipment reliability, and professional support from APIE’s team exceeded our expectations. The HYPERTEC machine performed flawlessly in challenging ground conditions, and the minimal surface disruption was crucial for our urban environment.”*
— Project Director, Municipal Water Authority

Why Choose APIE Pipe Jacking Solutions?

🔹 Advanced Technology: State-of-the-art laser guidance and navigation systems
🔹 Aplikasi Serbaguna: Suitable for sewer, water, gas, and utility installations
🔹 Global Support: International service centers across Europe, Middle East, Southeast Asia, and Americas
🔹 Customized Solutions: Tailored equipment configurations for specific project requirements
🔹 Comprehensive Service: From equipment supply to operation training and maintenance support