Project Overview
An aging earth-fill dam required rehabilitation after piezometric monitoring showed increasing seepage through its foundation. The remediation design specified a plastic concrete cut-off wall — a flexible slurry wall that tolerates deformation — installed through the dam body and foundation alluvium to an impervious layer. The alignment crossed highly heterogeneous ground: compacted dam fill, river alluvium with cobbles and boulders up to 800 mm, and moderately weathered rock at depth. Excavation depth reached 55 m, with cut-off wall thicknesses of 0.8 m. This combination of depth, boulder content, and strict permeability requirements made the trench cutter the only method able to guarantee continuity and verticality of the wall over the full alignment length of 620 m.
Project data
| Item | Detail |
| Project type | Dam remediation — plastic concrete cut-off wall (slurry trench) |
| Location | River dam site, South Asia |
| Cut-off wall length | 620 m alignment |
| Wall thickness | 0.8 m |
| Max. excavation depth | 55 m |
| Geology | Dam fill, alluvium with cobbles and boulders (up to 800 mm), weathered rock |
| Permeability requirement | k ≤ 1 × 10⁻⁶ cm/s |
| Equipment supplied | APIE TC-series trench cutter, desanding plant, slurry management system |
The Challenge
Conventional clamshell grabs had been used on adjacent sections and consistently struggled where boulder horizons were encountered: grab jaws bounced or skewed on oversized cobbles, panels stalled for days, and borehole logs could not capture boulder positions accurately enough for pre-drilling. The owner required guaranteed wall continuity to 55 m depth, verticality within 0.3% so that adjacent panels overlapped cleanly at all levels, and a permeability of 1 × 10⁻⁶ cm/s across the finished wall. Key technical risks:
- Boulders and cobbles interrupting grab excavation and damaging tooling.
- Trench stability in loose dam fill above the water table during slurry excavation.
- Consistent panel overlap at depth to avoid seepage windows between panels.
Our Solution: Trench Cutter Excavation with Slurry Support
APIE proposed a TC-series hydraulic trench cutter configuration with heavier cutter bodies and reinforced tool bits selected for boulder-rich ground. The counter-rotating wheels crush boulders progressively instead of displacing them, eliminating the stall risk of grab methods. Excavated spoil was pumped to a desanding plant, where separated slurry was reconditioned and returned to the trench, keeping bentonite consumption and disposal volumes low — an important cost and environmental advantage of slurry trench cutters on cut-off wall projects.
Equipment configuration for the cut-off wall
| Component | Role |
| APIE TC-series trench cutter | Continuous milling of fill, boulders and weathered rock to 55 m |
| Weighted cutter body + downthrust control | Positive penetration through cobble and boulder horizons |
| Inclination monitoring system | Real-time verticality readout, panel deviation ≤ 0.3% |
| Two-stage desanding plant | Slurry cleaning to sand content < 4% before plastic concrete placement |
| Slurry mixing and storage system | Bentonite slurry preparation, circulation and loss control |
Construction Process
The wall was executed in primary and secondary panels of 2.8 m cutting length. Plastic concrete, designed with a modulus consistent with the embankment, was tremie-placed as each panel reached design depth. Because the trench cutter mills the fresh plastic concrete of primary panels when forming secondary panels, panel joints are mechanically bonded rather than merely abutted — a fundamental quality benefit of cutter-excavated slurry walls for seepage control. Slurry levels were maintained above the groundwater table at all times, and ultrasonic monitoring confirmed panel geometry before every concrete pour.
Results
- 620 m of cut-off wall completed within the dry-season programme, with peak production of 60 m² per shift through boulder zones.
- All panels measured within 0.3% verticality, ensuring full-depth overlap between primary and secondary panels.
- Piezometric heads downstream of the dam dropped to design levels within one filling cycle; seepage flow reduced by more than 80%.
- Grab stall events eliminated; total excavation cost per square metre undercut the grab + pre-drilling alternative.
Following acceptance, the owner qualified trench cutter excavation as the reference method for the remaining dam rehabilitation phases, and the contractor added a second APIE trench cutter for the follow-up phases of the dam safety programme.
Why Trench Cutter Technology for Cut-Off Walls
For slurry trench cut-off walls deeper than roughly 25 m, or in ground containing boulders, cobbles, or hard rock, the hydraulic trench cutter offers unmatched advantages over grabs: continuous rather than cyclic excavation, built-in verticality correction, mechanical panel joints, and the ability to mill virtually any ground condition. APIE supplies trench cutters for diaphragm walls, plastic concrete cut-off walls, barrette piles, and cutter soil mixing, configured to your geotechnical data.
Contact APIE Foundation Equipment (China) Limited
Are you planning a diaphragm wall, cut-off wall, or barrette pile project that involves hard rock, boulders, or great depth? APIE Foundation Equipment (China) Limited supplies hydraulic trench cutters, diaphragm wall grabs, desanding plants, and complete foundation engineering equipment to contractors worldwide, together with technical support, spare parts, and operator training.
Send us your geotechnical profile, panel dimensions, and schedule, and our engineering team will recommend the most suitable trench cutter configuration and a competitive quotation within 24 hours.
Email: apie@apiepiling.com
WhatsApp: +86 189 2128 7030